12.15.2017 A look into one of our future classrooms12.15.2017 Another view of the addition from the hallway (classrooms are on the left)12.15.2017 Contractor discussing the vapor barrier with the team12.15.2017 Our Educational Planner and Chief Operations Officer checking out the construction work12.15.2017 Our Quality Assurance Manager reviewing some electrical box placements12.15.2017 The view from the addition looking through the courtyard at the existing school

12.15.2017 A look into one of our future classrooms

12.15.2017 Another view of the addition from the hallway (classrooms are on the left)

12.15.2017 Contractor discussing the vapor barrier with the team

12.15.2017 Our Educational Planner and Chief Operations Officer checking out the construction work

12.15.2017 Our Quality Assurance Manager reviewing some electrical box placements

12.15.2017 The view from the addition looking through the courtyard at the existing school

 
news and updates

January 2018: The roof and mezzanine are being framed in. 
December 2017: The team is working on the planning for interior murals in the building. There is a committee that includes students helping to develop the concept.
November 2017: Exterior walls have been framed! The fire main is done, tested, and approved. We also shut off the old waterline to cap the new one. Paving is scheduled for next month.
October 2017: Footings were poured and stem walls were put in. Digging for fire/water lines was completed and tested. We also completed paving of the bus loop.