March 27th, 2018: The groundbreaking ceremony is Friday 3/30 at 9:30am. We are excited to begin construction!
March 20th, 2018: We are working on signage and going over fence lines for the construction site.
March 12th, 2018: We have responded to comments from the county in an effort to move closer to getting our site development and building permits. We are working on planning our groundbreaking ceremony on the 30th. 
March 6th, 2018:
Our lowest qualified bidder is starting to pull together their paperwork. We need to have the contract signed to issue our notice to proceed. Our Project Manager (Mike Meadows) and Director of Educational Planning (Judy Piger) visited the school to observe traffic during drop off and pick up. 
March 5th, 2018:
The school board accepted the bid for the new project. We're moving forward!
February 27th, 2018:
Our bid opening was today. We had five contractors bid for the job and we have identified a lowest qualified bidder.
February 13th, 2018: We're still waiting on our permits. The person who checks plans at the county is on vacation for a few weeks. When he returns we should get comments back. We're also waiting on some letters so we can submit our D7 letter to the Office of the Superintendent of Public Instruction. We should be good to go in the next few days!
January 29th, 2018: Bid advertisements went on on 1/24/18 and the second will be out 1/31/18. The pre-bid walk through is on 2/8/18 and the Bid Opening is on 2/27/2018.
January 16th, 2018: We have reviewed all of the specs with our internal team and we're fine tuning our comments. 
January 2nd, 2018: We have reviewed the 95% Constructability plans and we're starting to respond back to the architect on those.
October 31st, 2017: We have received the 75% CD set on 10/13. We distributed it for review to our Internal Staff and Technology Department.
October 17th, 2017: We got the D6 form back.
October 10th, 2017: The project manager expects to have the permit set printed on Friday and it should be in hand next week.
September 26th, 2017: The team met this week to discuss the interior, bathrooms, and learning stairs.