March 27th, 2018: On Thursday we are presenting to our internal team of directors about the project.
March 20th, 2018: We're doing Value Engineering this week. We met with the team yesterday for a few hours and walked the construction site. Design development is scheduled to kick off on 4/2.
March 12th, 2018: We have our schematic documents. Our next Design Advisory Team meeting is coming up in early April. 
March 6th, 2018: We have Value Engineering scheduled to start a week from Monday.
February 27th, 2018: We're finishing up schematic design and the plans are at the cost estimator now. We're meeting with our architect this week to go over everything, and we'll meet with our internal department directors to go over the schematic design at the end of March.
December 12th, 2017: We are kicking off schematic design on Monday. The team is trying to finalize the traffic study we did so we can continue to move forward with that.
November 28th, 2017: There's a meeting on 11/29 to go through final posturing for preliminary design.
November 14th, 2017: We are continuing to work on concepts. We have not yet jumped into full schematic design. We had a community meeting and 13 were in attendance. Most attendees were neighbors that had questions regarding the construction process. The team did our best to address any questions or concerns.
October 30th, 2017: We received the 75% completed CD set on 10/13/17. It was distributed to our internal teams for review and comments.